kVA to amps, amps to kVA, and kW
Single- or three-phase, any voltage. Enter amps, kVA or kW and get the other two, plus a full-load amps table for standard transformer sizes.
Three-phase: use the line-to-line voltage (208, 480) and the line current. Power factor only matters for kW: kVA is apparent power, kW is real power. Use the equipment nameplate's power factor; 1.0 is right for resistive loads such as heaters.
Full-load amps = kVA × 1,000 ÷ V (single-phase) or ÷ (1.732 × V) (three-phase). Sizes are those in the federal efficiency tables for low-voltage dry-type distribution transformers. Size a transformer and its overcurrent protection under the NEC (Article 450) and the maker's data; this is an estimate.
Single-phase kVA = volts × amps ÷ 1,000; three-phase kVA = 1.732 × volts × amps ÷ 1,000, using line-to-line volts. A 480 V three-phase load drawing 100 A is 83.1 kVA. Turn it around for amps: a 75 kVA transformer at 208 V three-phase carries 208 A at full load. kW = kVA × power factor.
| kVA | 240 V single-phase | 208 V three-phase | 480 V three-phase |
|---|---|---|---|
| 1 kVA | 4.2 A | 2.8 A | 1.2 A |
| 1.2 kVA | 5.0 A | 3.3 A | 1.4 A |
| 3 kVA | 12.5 A | 8.3 A | 3.6 A |
| 5 kVA | 20.8 A | 13.9 A | 6.0 A |
| 7.5 kVA | 31.2 A | 20.8 A | 9.0 A |
| 10 kVA | 41.7 A | 27.8 A | 12.0 A |
| 15 kVA | 62.5 A | 41.6 A | 18.0 A |
| 25 kVA | 104.2 A | 69.4 A | 30.1 A |
| 30 kVA | 125.0 A | 83.3 A | 36.1 A |
| 37.5 kVA | 156.2 A | 104.1 A | 45.1 A |
| 45 kVA | 187.5 A | 124.9 A | 54.1 A |
| 50 kVA | 208.3 A | 138.8 A | 60.1 A |
| 58 kVA | 241.7 A | 161.0 A | 69.8 A |
| 75 kVA | 312.5 A | 208.2 A | 90.2 A |
| 100 kVA | 416.7 A | 277.6 A | 120.3 A |
| 112.5 kVA | 468.8 A | 312.3 A | 135.3 A |
| 150 kVA | 625.0 A | 416.4 A | 180.4 A |
| 165 kVA | 687.5 A | 458.0 A | 198.5 A |
| 225 kVA | 937.5 A | 624.5 A | 270.6 A |
| 300 kVA | 1,250.0 A | 832.7 A | 360.8 A |
| 500 kVA | 2,083.3 A | 1,387.9 A | 601.4 A |
Amps = kVA × 1,000 ÷ V (single-phase) or ÷ (1.732 × V) with line-to-line volts (three-phase), at full load.
How to use the kVA calculator
Pick the system
Single- or three-phase, the voltage, and whether you know amps, kVA or kW.
Enter the value
Plus the power factor if you're working with kW.
Read the results
kVA, amps and kW, the next standard transformer size, and full-load amps by size.
What the kVA calculator does
Three ways in
Amps to kVA, kVA to amps, or kW and power factor to kVA and amps.
Single and three-phase
Uses √3 (1.732) for three-phase with line-to-line voltage.
Transformer table
Full-load amps of standard sizes at 120 and 240 V single-phase, 208 and 480 V three-phase.
Next size up
Points to the next standard kVA rating at or above your load.
- Single-phase
- kVA = V × A ÷ 1,000
- Three-phase
- kVA = 1.732 × V(line-to-line) × A ÷ 1,000
- Real power
- kW = kVA × power factor
- Transformer sizes
- Low-voltage dry-type ratings listed in 10 CFR 431.196
- Not included
- Transformer overcurrent protection and conductor sizing (NEC Article 450, 240.21(C))
kVA Calculator FAQ
How do I convert kVA to amps?
Multiply kVA by 1,000 and divide by the voltage for single-phase, or by 1.732 × the voltage for three-phase. A 50 kVA single-phase transformer at 240 V carries 208 A; a 112.5 kVA three-phase at 480 V carries 135 A.
What is the difference between kVA and kW?
kVA is apparent power, volts times amps. kW is real power, the part that does work, equal to kVA times the power factor. Resistive loads such as heaters have a power factor near 1; motors and some electronics are lower, so their kW is less than their kVA.
Why do transformers use kVA instead of kW?
Because the heat in a transformer depends on current and voltage, not on the load's power factor. A transformer rated in kVA can carry that many volt-amps whatever the load's power factor.
How many amps is a 75 kVA transformer?
On a 208 V three-phase secondary, 75,000 ÷ (1.732 × 208) = 208 A. On the 480 V primary side, 90 A.
Can I size a transformer from this?
It gives the load in kVA and the standard size above it. Sizing the transformer, its overcurrent protection and the secondary conductors follows NEC Article 450 and 240.21(C), the equipment data and the AHJ, so treat this as an estimate.
Link to this tool
Found it useful? Paste this into your website, newsletter or resource page.
More free tools
All free toolsPrice it right, then book the job
CrewRobin is the AI front office for home-service shops: an AI receptionist that answers every call, qualifies the job and books it, plus missed-call text-back, quotes, invoices and review requests.